BOCATS cruise report, 17 June-31 July 2016
103 páginas, 28 figuras, The objectives of the BOCATS cruise are fulfilled in spite of the problems derived from
the installation of the new signal transmission cable. This operation delayed the departure by one
week. However, this delay was recovered thanks to the speed of the ship, the constant adaptation
of the cruise planning to the weather forecasts and the excellent reliability of the CTD and boxcorer
operations. A total of 138 CTD stations and 66 sediment sampling were done. In addition,
the recovery and new deployment of two ASFAR-ARGO systems were done, as well as the
deployment of five meteorological floats and nine ARGO floats, Project funded by MINECO, Ref. CTM2013-41048-P, Peer reviewed